Generator Registration Information
|
|
|
Article Content
|
 |
| Steps to Apply for Certification of Oregon RPS Eligibility |
|
1. Eligibility
2. WREGIS
Register your generating facility as a Generating Unit (GU) in WREGIS. (www.wregis.org).
3. Application
All applicants must complete a General Application. To help applicants understand what information is required, the Department has published an explanation of the application.
Supplemental applications may also be required, depending on the resource.
If your facility uses both renewable and non-renewable fuels to generate power, then a Multi-Fuel Supplement is also required.
Mail the General Application, required supplementals and documentation to RPS.application@state.or.us.
4. Response
The Department will review your submission and contact you with questions. Please note that there is no guaranteed response time. As a WREGIS registered generator, you are receiving RECs, but those RECs cannot be used for compliance until the Department certifies the unit as Oregon eligible.
5. Certification
Once approved, the Department will enter a unique Oregon certification number for your generating unit, or GU. The Department will also issue a formal letter to you advising you of your registry.
6. Renewal
An expiration date will also be issued, as Renewable Portfolio Standard eligibility adjusts each year with new legislative direction. A periodic review ensures that the unit’s generation remains eligible and that the facility's performance is within expectations. Please be aware of the expiration date and work with the Department to ensure renewal.
Contact:
Rebecca Sherman
RPS Program Administrator
Oregon Department of Energy
503-373-2295
Rebecca.Oneil@odoe.state.or.us
|
|
|
|
|